Client: Southern Program Alliance

Timeline: 8 months

New Chelsea station – Level Crossing Removal

Client

Southern Program Alliance

Services Provided

  • Design co-ordination
  • Electrical reticulation
  • Lighting installation
  • Power installation
  • Lighting contol
  • Exit & emergency control
  • Test and commission

Location

Chelsea, Victoria

Scope of Works

Electrical Works for the New Chelsea Station to:

  • Station buildings
  • Platforms including Platform Canopies.
  • Staircases, Ramps, Bridge and Supplies to two Lifts.
  • Shared User Path and general paths lighting.
  • Commuter car parks, drop off areas and bus stops lighting.
  • Public and Feature Lighting for Pedestrian Track crossings.

Specific electrical scope included supply and installation of:

  • LV main switchboard and main earthing system.
  • Isolation Transformers.
  • Sub distribution boards.
  • Temporary generator connection panel.
  • LV mains, submains, final sub-circuit and control cabling.
  • Lighting control equipment.
  • Electrical metering equipment.
  • Emergency lighting control and monitoring equipment.
  • Electrical and communication platform cable pits and conduits.
  • Electrical and communication cable trays and support brackets.
  • Electrical above ground conduit and wiring systems.
  • Light switches, socket outlets and isolators.
  • Luminaires and associated accessories and mounting brackets.
  • Emergency luminaires and exit signs.
  • Testing and commissioning.

Fast Facts

  • Design input at concept stage
  • Fast Paced Build under Occupation
  • 24/7 shifts during Track Occupation
  • Over 8000mt of conduit for Station cable reticulation installed
  • All Light and Power successfully completed for Station Opening at end of the Occupation