Client: John Holland, Metro Trains Melbourne
Timeline: June 2015 to December 2015
Ringwood Station & Bus Interchange Upgrade Project
Client
John Holland
Metro Trains Melbourne
Services Provided
Demolition, temporary supplies for Power and comms to existing station.
Supply, installation, testing, commissioning and maintenance of the electrical services associated.
Including all labour, plant, access equipment, supervision, materials, tariffs and equipment.
Location
Ringwood Station
Cnr. Wantirna Rd & Station St
Ringwood, VIC
Scope of Works
- Demolition of existing services and maintaining a working station. New Station concourse, revamp platforms, New carpark lighting and power, control and earthing systems. Fibre optics and communication cabling for the Myki installation.
- Complete integration of the existing station to the new station. To DDA compliant access, VicTrack and Metro requirements.
- MYKI station installation including wiring, installing and commissioning the Smart gates, CVM, SEM, FDP’s & NTTS Communication Cabinet.
Fast Facts
- Bus Interchange/Rail Station Upgrade
- Includes station forecourt, bus interchange, and Premium station facilities, covered public overpass
- Station remained functioning throughout project timeline