Client: John Holland – North West Program Alliance
Timeline: 15 months - Completed August 2021
New Coburg and Moreland Stations – Level Crossing Removal
Client
John Holland – North West Program Alliance
Services Provided
- Design co-ordination
- Electrical reticulation
- Lighting installation
- Power installation
- Lighting contol
- Exit & emergency control
- Test and commission
Location
Coburg, Victoria
Scope of Works
Electrical Works for the New Coburg and Moreland Stations to:
- Station buildings
- Elevated Platforms including Platform Canopies.
- Staircases, Ramps, Bridge and Supplies to two Lifts.
- Carpark, Inground services and lighting
- Shared User Path and general paths lighting.
Specific electrical scope included supply and installation of:
- LV main switchboard and main earthing system.
- Isolation Transformers.
- Sub distribution boards.
- Generator System.
- LV mains, submains, final sub-circuit and control cabling.
- Lighting control equipment.
- Electrical metering equipment.
- Emergency lighting control and monitoring equipment.
- Electrical and communication platform Junction Cabinets.
- Electrical and communication cable trays and support brackets.
- Electrical above ground conduit and wiring systems.
- Light switches, socket outlets and isolators.
- Luminaires and associated accessories and mounting brackets.
- Emergency luminaires and exit signs.
- Testing and commissioning.
Fast Facts
- Design collaboration at concept stage
- First of Only of combined Platform Cabinets
- Works carried out during Covid Pandemic